تعيين موارد للمهام
نوع: محتوى تعليمي
في Properties (خصائص) المهمة، انتقل إلى علامة تبويب Resources (الموارد)، ثم اختر Resource Name (اسم المورد) للمورد الذي تريد تعيينه لهذه المهمة. 1 اضغط على Ok (موافق). 2 عين الموارد لبقية المهام. 3
نوع: METADATA
وزارة التعليم
Ministry of Education
2023 - 1447
نوع: FIGURE_REFERENCE
شكل 1.33: تعيين الموارد للمهام
نوع: METADATA
74
🔍 عناصر مرئية
Gantt Chart Interface with Resource Assignment Dialog
A screenshot of a Gantt chart software interface. The main window shows a project timeline with tasks like 'Problem definition', 'Research and analysis', 'Concept generation', 'Design selected', 'Design development', 'Prototyping', 'Design optimization', 'Implementation'. A dialog box titled 'Properties for Problem definition' is open, with the 'Resources' tab selected. Inside the dialog, there's a table with columns 'ID', 'Resource Name', 'Unit', 'Coordinator', 'Role'. The 'Resource Name' column shows a dropdown list with names: Ahmed, Ali, Khaled, Fahd, Nasser, Osama. A blue circle with '1' points to the selected 'Ahmed' in the dropdown. To the right, a 'Task cost' section shows 'Calculated: 0.0' and 'Set explicitly: 0.0'. At the bottom of the dialog, 'Ok' and 'Cancel' buttons are visible, with a blue circle with '2' pointing to the 'Ok' button. The main Gantt chart shows 'Zoom In', 'Zoom Out', 'Project start', 'Past Future', 'Show critical path', 'Baselines' options and '2023' as the year.
Gantt Chart displaying project tasks and assigned resources
A screenshot of a Gantt chart displaying a project schedule. The left panel lists tasks and their assigned resources with their default roles: Ahmed (project manager), Ali (Design Engineer), Khaled (Research Engineer), Fahd (CAD Engineer), Nasser (Manufacturing Engineer), Osama (Testing Engineer). The right panel shows a timeline from Week 13 (3/26/23) to Week 22 (5/28/23) in 2023. Horizontal bars represent tasks, with some bars colored blue and some red, indicating progress or resource allocation over time. A blue circle with '3' points to the timeline area, indicating the visual representation of assigned resources and task durations. The chart also shows options like 'Zoom In', 'Zoom Out', 'Project start', 'Past Future', 'Show critical path', 'Baselines'.
📄 النص الكامل للصفحة
--- SECTION: تعيين موارد للمهام --- في Properties (خصائص) المهمة، انتقل إلى علامة تبويب Resources (الموارد)، ثم اختر Resource Name (اسم المورد) للمورد الذي تريد تعيينه لهذه المهمة. 1 اضغط على Ok (موافق). 2 عين الموارد لبقية المهام. 32023 - 1447شكل 1.33: تعيين الموارد للمهام--- VISUAL CONTEXT ---
**FIGURE**: Gantt Chart Interface with Resource Assignment Dialog Description: A screenshot of a Gantt chart software interface. The main window shows a project timeline with tasks like 'Problem definition', 'Research and analysis', 'Concept generation', 'Design selected', 'Design development', 'Prototyping', 'Design optimization', 'Implementation'. A dialog box titled 'Properties for Problem definition' is open, with the 'Resources' tab selected. Inside the dialog, there's a table with columns 'ID', 'Resource Name', 'Unit', 'Coordinator', 'Role'. The 'Resource Name' column shows a dropdown list with names: Ahmed, Ali, Khaled, Fahd, Nasser, Osama. A blue circle with '1' points to the selected 'Ahmed' in the dropdown. To the right, a 'Task cost' section shows 'Calculated: 0.0' and 'Set explicitly: 0.0'. At the bottom of the dialog, 'Ok' and 'Cancel' buttons are visible, with a blue circle with '2' pointing to the 'Ok' button. The main Gantt chart shows 'Zoom In', 'Zoom Out', 'Project start', 'Past Future', 'Show critical path', 'Baselines' options and '2023' as the year.
Table Structure:
Headers: ID | Resource Name | Unit | Coordinator | Role Rows:
Row 1: 1 | Ahmed | 100.0 | |
Empty cells: Coordinator and Role for the resource 'Ahmed'
Calculation needed: N/A Data: The dialog shows resource assignment options for a specific task. The main chart shows a timeline from Week 13 to Week 22.
Key Values: Gantt, Resources Chart, Zoom In, Zoom Out, Project start, Past Future, Show critical path, Baselines, 2023, Name, Begin date, End date, Problem definition, 4/4/23, 4/8/23, Research and analysis, 4/9/23, 4/16/23, Concept generation, 4/16/23, 4/20/23, Design selected, 4/20/23, 4/20/23, Design development, Prototyping, Design optimization, Implementation, Properties for Problem definition, General, Predecessors, Resources, Custom Columns, Add, Delete, ID, Resource Name, Unit, Coordinator, Role, 1, Ahmed, 100.0, Ali, Khaled, Fahd, Nasser, Osama, Task cost, Calculated: 0.0, Set explicitly: 0.0, Ok, Cancel Context: This figure illustrates the first two steps of assigning resources to a task in a project management software, specifically selecting a resource from a dropdown list and confirming the selection.**FIGURE**: Gantt Chart displaying project tasks and assigned resources Description: A screenshot of a Gantt chart displaying a project schedule. The left panel lists tasks and their assigned resources with their default roles: Ahmed (project manager), Ali (Design Engineer), Khaled (Research Engineer), Fahd (CAD Engineer), Nasser (Manufacturing Engineer), Osama (Testing Engineer). The right panel shows a timeline from Week 13 (3/26/23) to Week 22 (5/28/23) in 2023. Horizontal bars represent tasks, with some bars colored blue and some red, indicating progress or resource allocation over time. A blue circle with '3' points to the timeline area, indicating the visual representation of assigned resources and task durations. The chart also shows options like 'Zoom In', 'Zoom Out', 'Project start', 'Past Future', 'Show critical path', 'Baselines'.
Table Structure:
Headers: Name | Default role Rows:
Row 1: Ahmed | project manager Row 2: Ali | Design Engineer Row 3: Khaled | Research Engineer Row 4: Fahd | CAD Engineer Row 5: Nasser | Manufacturing Engineer Row 6: Osama | Testing Engineer Calculation needed: N/A Data: The chart visually represents the duration and allocation of resources for various project tasks over a period of several weeks in 2023. Different colored bars likely indicate different task statuses or resource types.
Key Values: Gantt, Resources Chart, Zoom In, Zoom Out, Project start, Past Future, Show critical path, Baselines, 2023, Name, Default role, Ahmed, project manager, Ali, Design Engineer, Khaled, Research Engineer, Fahd, CAD Engineer, Nasser, Manufacturing Engineer, Osama, Testing Engineer, Week 13, 3/26/23, Week 14, 4/2/23, Week 15, 4/9/23, Week 16, 4/16/23, Week 17, 4/23/23, Week 18, 4/30/23, Week 19, 5/7/23, Week 20, 5/14/23, Week 21, 5/21/23, Week 22, 5/28/23
Context: This figure demonstrates the overall project schedule and resource assignments as visualized in a Gantt chart, showing how different team members contribute to various stages of the project.