لتغيير خصائص المهمة:
نوع: محتوى تعليمي
من قائمة Tasks (المهام)، حدد أمر Task Properties (خصائص المهمة). 1
اضبط Begin Date (تاريخ البدء) من خلال الضغط على الزر المجاور لحقل النص. 2
أضف Duration (مدة) المهمة لتكون عدد أيام العمل. 3
اضغط على Ok (موافق). 4
نوع: METADATA
وزارة التعليم
2023 - 1447
نوع: METADATA
67
نوع: FIGURE_REFERENCE
شكل 1.26: تغيير خصائص المهمة
🔍 عناصر مرئية
GanttProject Main Interface with Tasks Menu Open
A screenshot of the GanttProject software interface. The main window shows a project timeline for 'April 2023' and a task list with 'Problem definition' scheduled for '4/4/23'. The menu bar includes 'Project', 'Edit', 'View', 'Tasks', 'Resources', 'Help'. The 'Tasks' menu is open, displaying options: 'New task Ctrl-T', 'Task Properties... Alt-Enter', and 'Delete Task Delete'. A circled '1' points to 'Task Properties...'.
Properties for Problem definition Dialog (Duration Input)
A dialog box titled 'Properties for Problem definition' is shown. The 'General' tab is selected. Fields include 'Name' ('Problem definition'), 'Milestone' (checkbox), 'Begin date' ('April 4, 2023'), 'End date' ('April 4, 2023'), and 'Duration'. The 'Duration' field contains the value '3', indicated by a circled '3'. Below, 'Earliest begin' (checkbox, 'April 2, 2023', 'Copy begin date'), 'Priority' ('Normal'), 'Progress' ('0'), 'Show in timeline' (checkbox), 'Shape', 'Colors' ('Choose...', 'Default'), and 'Web Link' are visible. 'Ok' and 'Cancel' buttons are at the bottom, with 'Ok' indicated by a circled '4'.
Properties for Problem definition Dialog (Begin Date Calendar Selection)
A dialog box titled 'Properties for Problem definition' is shown, with the 'General' tab selected. The 'Begin date' field, currently 'April 4, 2023', is highlighted by a circled '2'. A calendar pop-up for 'April 2023' is displayed, showing days of the week (Sun, Mon, Tue, Wed, Thu, Fri, Sat) and dates 1 through 30. Dates 4 and 7 are visually distinct (e.g., highlighted). Below the calendar, 'Today is 07 April 2023' is visible.
📄 النص الكامل للصفحة
--- SECTION: لتغيير خصائص المهمة: --- من قائمة Tasks (المهام)، حدد أمر Task Properties (خصائص المهمة). 1
اضبط Begin Date (تاريخ البدء) من خلال الضغط على الزر المجاور لحقل النص. 2
أضف Duration (مدة) المهمة لتكون عدد أيام العمل. 3
اضغط على Ok (موافق). 42023 - 1447شكل 1.26: تغيير خصائص المهمة--- VISUAL CONTEXT ---
**SCREENSHOT**: GanttProject Main Interface with Tasks Menu Open Description: A screenshot of the GanttProject software interface. The main window shows a project timeline for 'April 2023' and a task list with 'Problem definition' scheduled for '4/4/23'. The menu bar includes 'Project', 'Edit', 'View', 'Tasks', 'Resources', 'Help'. The 'Tasks' menu is open, displaying options: 'New task Ctrl-T', 'Task Properties... Alt-Enter', and 'Delete Task Delete'. A circled '1' points to 'Task Properties...'.
Data: The main project view shows a Gantt chart for April 2023. A task named 'Problem definition' is listed with 'Begin date' and 'End date' both as '4/4/23'. The 'Tasks' menu is active, showing 'Task Properties...' as the selected option.
Key Values: GanttProject, Tasks menu, Task Properties..., April 2023, Problem definition, Ctrl-T, Alt-Enter Context: Illustrates the initial step of accessing task properties through the 'Tasks' menu in GanttProject.**SCREENSHOT**: Properties for Problem definition Dialog (Duration Input)
Description: A dialog box titled 'Properties for Problem definition' is shown. The 'General' tab is selected. Fields include 'Name' ('Problem definition'), 'Milestone' (checkbox), 'Begin date' ('April 4, 2023'), 'End date' ('April 4, 2023'), and 'Duration'. The 'Duration' field contains the value '3', indicated by a circled '3'. Below, 'Earliest begin' (checkbox, 'April 2, 2023', 'Copy begin date'), 'Priority' ('Normal'), 'Progress' ('0'), 'Show in timeline' (checkbox), 'Shape', 'Colors' ('Choose...', 'Default'), and 'Web Link' are visible. 'Ok' and 'Cancel' buttons are at the bottom, with 'Ok' indicated by a circled '4'.
Data: The dialog shows task details. The 'Duration' is explicitly set to '3'. The 'Ok' button is highlighted as the final action.
Key Values: Properties for Problem definition, General tab, Name: Problem definition, Begin date: April 4, 2023, End date: April 4, 2023, Duration: 3, Ok button, Cancel button, April 2, 2023, Normal, 0
Context: Demonstrates how to input the duration for a task and finalize the changes in the task properties dialog.**SCREENSHOT**: Properties for Problem definition Dialog (Begin Date Calendar Selection)
Description: A dialog box titled 'Properties for Problem definition' is shown, with the 'General' tab selected. The 'Begin date' field, currently 'April 4, 2023', is highlighted by a circled '2'. A calendar pop-up for 'April 2023' is displayed, showing days of the week (Sun, Mon, Tue, Wed, Thu, Fri, Sat) and dates 1 through 30. Dates 4 and 7 are visually distinct (e.g., highlighted). Below the calendar, 'Today is 07 April 2023' is visible.
Data: The calendar shows the month of April 2023. The 4th and 7th of April are marked. The current date is indicated as April 7th, 2023. The 'Begin date' field is associated with this calendar selection.
Key Values: Properties for Problem definition, General tab, Begin date: April 4, 2023, April 2023 calendar, Today is 07 April 2023, Sun, Mon, Tue, Wed, Thu, Fri, Sat, 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30
Context: Illustrates the process of selecting a 'Begin date' for a task using the integrated calendar tool within the task properties dialog.
🎴 بطاقات تعليمية للمراجعة
عدد البطاقات: 4 بطاقة لهذه الصفحة
ما هي الخطوات الأساسية لتغيير خصائص مهمة في برنامج GanttProject؟
الإجابة: 1. من قائمة Tasks (المهام)، حدد أمر Task Properties (خصائص المهمة). 2. اضبط Begin Date (تاريخ البدء) من خلال الضغط على الزر المجاور لحقل النص. 3. أضف Duration (مدة) المهمة لتكون عدد أيام العمل. 4. اضغط على Ok (موافق).
الشرح: هذه الخطوات تمثل الإجراء المنهجي لتعديل خصائص أي مهمة في برنامج إدارة المشاريع GanttProject، بدءاً من الوصول إلى خصائص المهمة وانتهاءً بتأكيد التغييرات.
تلميح: ركز على التسلسل المنطقي للخطوات الأربع المذكورة في النص.
التصنيف: صيغة/خطوات | المستوى: سهل
ما هو الغرض من أمر 'Task Properties' في برنامج GanttProject؟
الإجابة: الغرض منه هو فتح نافذة أو مربع حوار يسمح للمستخدم بتعديل وتغيير خصائص المهمة المحددة، مثل تاريخ البدء والمدة.
الشرح: أمر 'Task Properties' هو نقطة الدخول الرئيسية لتخصيص وإعداد تفاصيل أي مهمة ضمن مشروع، مما يجعله أداة أساسية في تخطيط وجدولة المشاريع.
تلميح: فكر في الكلمة الإنجليزية 'Properties' وما تعنيه في سياق البرامج الحاسوبية.
التصنيف: مفهوم جوهري | المستوى: سهل
كيف يتم تحديد 'تاريخ البدء' (Begin Date) لمهمة في نافذة خصائص المهمة؟
الإجابة: يتم تحديد تاريخ البدء من خلال الضغط على الزر المجاور لحقل النص الخاص بـ 'Begin Date'، مما يفتح تقويماً يسمح باختيار التاريخ المناسب.
الشرح: استخدام تقويم منبثق (pop-up calendar) هو طريقة رسومية شائعة وبديهية لاختيار التواريخ في واجهات البرامج، مما يقلل من أخطاء الإدخال اليدوي.
تلميح: تذكر أن الإجراء يتضمن زراً بجانب الحقل النصي وليس الكتابة المباشرة.
التصنيف: صيغة/خطوات | المستوى: سهل
ما المقصود بـ 'Duration' في سياق إدارة المهام ضمن برنامج GanttProject؟
الإجابة: المقصود بـ 'Duration' هو مدة المهمة، والتي يتم تحديدها بعدد أيام العمل المطلوبة لإنجاز تلك المهمة.
الشرح: حقل 'المدة' (Duration) هو معيار أساسي في تخطيط المشاريع، حيث يحدد الإطار الزمني المتوقع لتنفيذ نشاط معين، مما يؤثر على الجدول الزمني الكلي للمشروع.
تلميح: اربط الكلمة الإنجليزية 'Duration' بمفهوم الزمن أو الفترة الزمنية.
التصنيف: تعريف | المستوى: سهل